Advantages of a bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by drawings and specifications in the tender documentation for construction works.
A bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
At some stage in a project’s procurement process, regardless of the type of contract being used, the works will need to be quantified in order to obtain prices or to value the extent of the work and variations to issue payments. A good and accurate BoQ makes this process much easier and more transparent, and removes the reliance on guesswork. Before construction begins, the BoQ can inform the project budget and the modification of any elements of the design that may be prohibitively expensive. It can also help clarify quantities which means the correct materials can be procured in advance of the works starting.
A BoQ can provide a clear and extensive statement of the work that is to be completed, as well as a reliable base for budget control and accurate cost reporting. It enables the preparation of cash flow forecasts and provides a basis for the valuation of variations, the preparation of interim payments, and the final account.
For tenderers, it helps create a low-risk and low-cost tendering environment, which encourages the submission of competitive bids since the risk is better understood and defined.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Bill.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- CESMM4.
- Common mistakes in bill of quantities.
- Cost plans.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- Taking off.
- Tender.
- Types of bill of quantities.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.